Richmond County
Route 637 (County Bridge Road)
County Bridge Road is closed to through traffic at the bridge over Cat Point Creek due to damage following heavy rain and flooding in summer 2021. A bridge replacement is under construction. County Bridge Road will remain closed to through traffic until the new bridge reopens by April 2024.
Spotsylvania County
I-95 Southbound Exit 126 Off-Ramp and Route 1 Southbound
A second right turn lane is under construction from the I-95 southbound off-ramp at exit 126 onto Route 1 southbound. Route 1 southbound is being widened from the off-ramp to Southpoint Parkway with an additional turn lane. A second right turn lane is being added from Route 1 southbound to Southpoint Parkway. Traffic islands will be installed along Southpoint Parkway as a safety improvement to allow left turns into driveways but restrict through and left-turning traffic exiting from side streets. Additional right turn lane added to Southpoint Parkway to Route 1 southbound. Project completion in Aug. 2025.
Route 3 and Orange Plank Road
Utility relocation is underway ahead of construction to modify the intersection of Route 3 and Orange Plank Rd. to a new traffic pattern to enhance safety, improve traffic flow, and reduce conflict points. Project completion in spring 2024.
Route 17 (Mills Drive) Overpass Replacement and Widening
Construction started in Dec. 2020 to replace the existing two-lane interstate overpass on Route 17 with a four-lane bridge. Route 17 is being widened to four lanes until just east of the Hospital Boulevard/Germanna Point Drive intersection. A shared-use path, sidewalk, and pedestrian crossing equipment will be added as part of the project. Project completion was scheduled for late Feb. 2024. The project is now anticipated to be completed in May 2024.
Route 208 (Courthouse Road) and Hood Drive
Hood Drive is reduced to a single lane between Route 1 and Route 208 (Courthouse Road), carrying only northbound traffic. Southbound traffic should follow the posted detour along Courthouse Road and Route 1 southbound. New right and left turn lanes are under construction at an entrance to a future U.S. Veterans Health Administration outpatient clinic. Additional turn lanes will be built on northbound Hood Drive approaching Courthouse Road. A raised median on Hood Drive will separate northbound and southbound traffic between Courthouse Road and McGowan Drive. Additional sidewalks, crosswalks, and pedestrian crossing equipment will be installed at the intersection. Project completion in June 2024.
Route 606 (Mudd Tavern Road) Widening
Mudd Tavern Road is being widened to four lanes between I-95 and Route 1. A new secondary access route, Route 2092, will be built parallel to Mudd Tavern Road, and will connect with South Roxbury Mill Road and Dan Bell Lane. Project completion in May 2025.
Westmoreland County
Route 658 (Monroe Bay Circle)
Monroe Bay Circle is reduced to a single travel lane with a temporary bridge spanning Monroe Creek. A temporary traffic signal is directing one-way, alternating traffic. The bridge is a temporary measure to maintain traffic flow while a bridge replacement project is advanced.
Commuting and Ridesharing Information
GWRideConnect is a free ridesharing information and matching service for the Fredericksburg area, part of the George Washington Regional Commission.