From VDOT:
I-95 Southbound
Exit 148 (Quantico)
Tuesday – Friday, 9 p.m. – 10 a.m. and Thursday – Friday, 9 p.m. – 6 a.m. Single southbound lane closure starting at 9 p.m. followed by double lane closures at 10 p.m. for pothole repairs and construction activities for Improve95 projects. Double lane closures will end at 4:30 a.m. A single southbound lane will remain closed until 10 a.m. except on Friday, when all lanes will reopen by 6 a.m.
Exit 136 (Centreport Parkway)
Tuesday – Friday, 9 p.m. – 10 a.m. and Thursday – Friday, 9 p.m. – 6 a.m. Single southbound lane closure starting at 9 p.m. followed by double lane closures at 10 p.m. for pothole repairs and construction activities for Improve95 projects. Double lane closures will end at 4:30 a.m. A single southbound lane will remain closed until 10 a.m. except on Friday, when all lanes will reopen by 6 a.m.
Exit 133 (Route 17)
Tuesday – Friday, 5 a.m. – 10 a.m. Single southbound lane closure at mile marker 134 just before the Exit 133 interchange for construction activities for Improve95 projects.
Exit 133 (Route 17) to Exit 130 (Route 3)
Tuesday – Friday, 9 p.m. – 4:30 a.m. and Thursday – Friday, 9 p.m. – 6 a.m. Single southbound lane closure at 9 p.m. followed by double lane closures at 10 p.m. for construction activities for Improve95 projects. Double lane closures will end at 4:30 a.m. A single southbound lane will remain closed until 10 a.m. except on Friday, when all lanes will reopen by 6 a.m.
Exit 126 (Spotsylvania) to Exit 118 (Mudd Tavern Road)
Tuesday – Friday, 9 p.m. – 5 a.m. Mobile operation with single to double lane closures for milling and paving the travel lanes south of Exit 126 at mile marker 121 to mile marker 117, which is near the Exit 118 interchange.
I-95 Northbound
Exit 98 (Doswell) to I-95 Northbound Safety Rest Area
Wednesday – Thursday, 9 p.m. – 5 a.m. Mobile operation with single to double lane closures for milling and paving the travel lanes north of Exit 98/Doswell at mile marker 101 to mile marker 108, which is near the I-95 Northbound Safety Rest Area and Welcome Center. Crews will also close the off-ramp periodically when necessary between these hours at exit 104 (Route 207/Rogers Clark Boulevard). Northbound travelers seeking Route 207 are advised to use exit 110 (Route 639/Ladysmith Road) to I-95 southbound then use the southbound ramps to access Route 207 as the recommended detour. Drivers should use the most convenient alternate route to Route 207 depending on their destination.
Exit 148 (Quantico)
Tuesday – Wednesday, 9 p.m. – 4:30 a.m. Single northbound lane closure for construction activities for Improve95 projects.
Stafford County
Route 1 Southbound
Tuesday – Friday, 9 a.m. – 3 p.m. Single southbound lane closure for Potomac Creek bridge replacement, between Potomac Creek Lane and Centreport Parkway intersection.
Route 3 Westbound
24-hour-lane closure. Right westbound lane on Route 3 between Route 607 and Route 218 at the bridge over CSX for work under the bridge.
Hospital Center Boulevard
Tuesday – Thursday, 9:30 a.m. – 3 p.m. and Friday, 9:30 a.m. – 2 p.m. Single lane closures on Hospital Center Boulevard between Route 1 and Austin Ridge Drive for Improve95 projects construction.
Spotsylvania County
Route 3 (Plank Road)
Tuesday – Friday, 8 p.m. – 5 a.m. Alternating single lane closures on Route 3 between Chewning Drive and Bragg Road for pavement marking work.
Route 3 Eastbound
Tuesday – Thursday, 8 p.m. – 5 a.m. Mobile operation with alternating lane closures on Route 3 eastbound between Elys Ford Road and Andora Drive for milling and paving.
Route 620 (Harrison Road)
Monday – Friday, 9 a.m. – 3 p.m. Single lane closures on Harrison Road with one-way, alternating traffic between the I-95 overpass and Salem Station Boulevard for tree clearing associated with water line placement. Construction for development under permit.
Route 639 (Leavells Road/Salem Church Road)
Tuesday – Thursday, 7 p.m. – 6 a.m. Milling and paving. Mobile single lane closures for road resurfacing work between Route 3 and Route 208. Motorists can expect a temporary rough surface in milled areas.
Caroline County
Route 207
Wednesday – Thursday, 8 p.m. – 5 a.m. Alternating single lane closure on Route 207 from Route 1 to Route 652 (Carmel Church Loop) for milling and paving. Flaggers will direct drivers through the work zone.
Route 207 near I-95
Wednesday – Friday, 8 a.m. – 4 p.m. Single lane closure on Route 207 eastbound and westbound near I-95 for guardrail repair.
Route 625 (Passing Road/Supply Road)
Thursday – Friday, 7 a.m. – 7 p.m. Alternating single lane closure on Route 625 between the Essex County line and the King & Queen County line for surface treatment. Drivers will direct traffic through the work zone.
Route 722 (Nelson Hill Road)
Wednesday – Friday, 8 a.m. – 4 p.m. Single lane closure on Nelson Hill Road near Industrial Drive for guardrail repair. A flagging crew will direct drivers in the work zone.
Surface Treatment
Drivers should expect alternating single lane closures on the following routes for surface treatment. Flaggers will direct drivers through each work zone.
Tuesday – Friday, 7 a.m. – 7 p.m.
- Route 603 (Countyline Church Road)
- Route 605 (Paige Road)
- Route 1038 (Baymeadow Court)
- Route 1039 (Baybreeeze Court)
- Route 1040 (Watermans Boulevard)
- Route 1041 (Portobago Trail)
- Route 1042 (Goose Point Court)
- Route 1043 (Canvasback Court)
Essex County
Route 619 (Sunnyside Road)
Wednesday – Friday, 8 a.m. – 5 p.m. Drivers should expect delays on Route 619 at the intersection with Route 623 (Beulah Church Road) and Route 650 (Hickory Hill Road) for the installation and removal of highway signs. Flaggers will direct drivers through the work zone.
Route 620 (Dunnbrooke Road)
Wednesday – Friday, 8 a.m. – 5 p.m. Drivers should expect delays on Route 620 at the intersection with Route 647 (Hales Bridge Road) and Route 642 (Purkins Road) for the installation and removal of highway signs. Flaggers will direct drivers through the work zone.
Route 629 (Battery Road)
Wednesday – Friday, 8 a.m. – 5 p.m. Drivers should expect delays on Route 629 at the intersection with Route 624 (Essex Church Road) and Route 628 (Femlea Road) for the installation and removal of highway signs. Flaggers will direct drivers through the work zone.
Route 652 (Signboard Road)
Wednesday – Friday, 8 a.m. – 5 p.m. Drivers should expect delays on Route 652 at the intersection with Route 653 (Burruss Road) and Route 602 (Concord Road) for the installation and removal of highway signs. Flaggers will direct drivers through the work zone.
King George County
Route 605 (Bloomsbury Road)
Wednesday, 7 a.m. – 7 p.m. Alternating one-way traffic on Bloomsbury Road between Route 3 and Route 218 for paving. Flaggers will direct drivers in the work zone.
Route 609 (Comorn Road)
Wednesday – Friday, 7 a.m. – 7 p.m. Alternating one-way traffic on Comorn Road between Stanley Road and Route 218 for paving. Flaggers will direct drivers in the work zone.
Route 610 (Indiantown Road)
Tuesday – Thursday, 7 a.m. – 7 p.m. Alternating one-way traffic on Indiantown Road between Route 3 and Route 206 (Dahlgren Road) for paving. Flaggers will direct drivers in the work zone.
Route 623 (Jersey Road)
Road closure. Jersey Road is closed to through traffic near the Rt. 301 intersection for an emergency pipe replacement project. Road is anticipated to remain closed until Aug. 2021. Detour route is posted along Route 301 and Route 3.
King William County
Route 360 Eastbound
Wednesday – Thursday, 7 a.m. – 7 p.m. Drivers should expect alternating single lane closures on Route 360 eastbound from the east end of the Moncuin Creek bridge to the King and Queen County line for pavement marking.
Lancaster County
Centerline Rumble Strips
Tuesday – Friday, 7 a.m. – 7 p.m. Mobile single lane closures as crews install centerline rumble strips on the following routes:
- Route 201 (White Chapel Road/Courthouse Road)
- Route 222 (Weems Road)
Middlesex County
Route 3 (General Puller Highway)
Friday, 7 a.m. – 7 p.m. Mobile operation for milling and paving with alternating single lane closures between Regent Road and Twiggs Ferry Road.
Surface Treatment
Tuesday – Friday, 7 a.m. – 7 p.m. Mobile single lane closures as crews apply surface treatment on the following routes:
- Route 605 (Canoe House Road)
- Route 606 (Glebe Landing Road/Briery Swamy Road)
- Route 607 (Dragon Road)
- Route 666 (Croxton’s Road)
Northumberland County
Surface Treatment
Tuesday – Friday, 7 a.m. – 7 p.m. Mobile single lane closures as crews apply surface treatment on the following routes:
- Route 1215 (Peninsula Drive)
- Route 1218 (Penn Court)
- Route 1413 (Carolina Drive)
- Route 1414 (Howard Court)
- Route 1415 (Holiday Drive)
Richmond County and Town of Tappahannock
Route 360 over the Rappahannock River: Downing Bridge
Tuesday – Thursday, 9 p.m. – 6 a.m. One-way, alternating traffic on Route 360 on the Downing Bridge over the Rappahannock River between Richmond County and the Town of Tappahannock. Bridge maintenance to repair bridge deck, bridge joints. Traffic will be directed by automated flagging assistance devices.
Additional Construction Projects in
Fredericksburg District
Caroline County
Route 17 Emergency Repair
An emergency repair project is underway on Route 17 (Tidewater Trail) in Caroline County between Mount Road and Ware Creek Road to stabilize an adjacent slope and drainage pipe underneath the road. Route 17 is open to traffic, but motorists can expect one-way, alternating traffic controlled by a temporary traffic signal, or intermittent direction by a flagging crew. There is no vehicle height or width restriction in the work zone, and vehicles of all legal loads may pass through this area. Repairs are anticipated to be complete in June 2021.
Route 207 Southbound Bridge Replacement
Route 207 is reduced to a single northbound and southbound lane at the bridge over the Mattaponi River. Traffic is traveling in the northbound lanes while the southbound bridge is closed for a replacement project. The new southbound bridge is anticipated to open to traffic in Sept. 2021.
Route 743 (Clifton Road) over South River
Construction began in December 2020 to replace a structurally deficient timber bridge on Clifton Road over the South River. The existing bridge is open during construction. The new bridge will be a concrete structure, and will allow heavier vehicles to cross. The new bridge is scheduled to open in Oct. 2021.
City of Fredericksburg
Route 3 Business at Chatham Bridge
The Chatham Bridge is closed to traffic for an improvement project. Drivers should follow the posted detour signs directing traffic around the bridge closure. The bridge will reopen to traffic in Oct. 2021, and all construction work will be complete by April 2022.
Gloucester County
Pedestrian Improvements at Route 17 and Route 17 Business (Main Street)
Construction is substantially complete on a project to build sidewalk, crosswalks, pedestrian refuge islands, and new pedestrian crossing equipment at the northern intersection of Route 17 and Route 17 Business, and at Route 17 and McFadden Way. Pedestrian crossing signal equipment scheduled to be installed in summer 2021.
Gloucester County and King and Queen County
Route 14 Bridge Replacement over Poropotank Creek
Route 14 is closed to through traffic at Poropotank Creek for a bridge replacement project. The bridge is located at the Gloucester County and King and Queen County line. Traffic is detoured to use Route 17 and Route 33 during the project. The road is scheduled to reopen in July 2021.
Gloucester County and Middlesex County
Route 17 Southbound over Dragon Run
Route 17 southbound is reduced to a single lane for a bridge rehabilitation project over Dragon Run. The bridge is located at the county line between Gloucester County and Middlesex County. Project estimated completion is Aug. 2021.
King George County
Route 301 Slope Repair
Route 301 southbound near Route 616 (Washington Mill Road) has been reduced to one lane in King George County for motorist safety due to the failure of an adjacent slope. An emergency repair is underway. The lane is anticipated to reopen by early August 2021.
Route 623 (Jersey Road)
Jersey Road is closed to through traffic near the Rt. 301 intersection for an emergency pipe replacement project. Road is anticipated to remain closed until Aug. 2021. Detour route is posted along Route 301 and Route 3.
King William County
Route 662 (Sharon Road)
A portion of Sharon Road is closed for reconstruction following damage from Tropical Storm Michael. A project to reconstruct a slope and replace a culvert is anticipated to begin in spring 2021, and will reopen to traffic in summer 2021.
Middlesex County
Route 625 (Barrick’s Mill Road) Bridge Replacement
A portion of Barrick’s Mill Road is closed to traffic at Mill Creek through September 2021 while crews replace the existing bridge over Barrick’s Mill Creek. Drivers on Barrick’s Mill Road will be detoured around the 24-hour road closure using the following routes:
Route 625 (Barrick’s Pond Road)
Route 626 (Wake Road)
Route 624 (Regent Road)
Northumberland County
Route 202 (Hampton Hall Road)
Hampton Hall Road is closed to through traffic east of Route 619 (Deer Run Road) due to damage following heavy rain and flooding on June 11. Motorists should continue to follow the posted detour route for this closure:
- Route 617 (Lively Hope Road)
- Route 600 (Gibeon Road)
- Route 360 (Richmond Road)
Route 202 is anticipated to reopen to traffic in mid-July 2021 after repairs are complete.
Richmond County
Route 637 (County Bridge Road)
County Bridge Road is closed to through traffic at the bridge over Cat Point Creek due to damage following heavy rain and flooding on June 11. A timeline to restore and reopen the road is still under development.
Stafford County
Route 1 at Potomac Creek
Construction is underway to replace the Route 1 bridge over Potomac Creek in Stafford County. Route 1 will continue to have four travel lanes open during the project, with only periodic single lane closures required. The new bridge will be complete in July 2022.
Spotsylvania County
Route 17 Overpass Replacement and Widening
Construction started in December 2020 on a project to replace the existing two-lane interstate overpass on Route 17 with a four-lane bridge. Route 17 will be widened to four travel lanes to just east of the Hospital Boulevard/Germanna Point Drive intersection. Sidewalk, a shared-use path, and pedestrian crossing equipment will be added as part of the project. Improvements will be completed in Feb. 2024.
Town of West Point and New Kent County
Route 30/33 (Eltham Bridge)
Eastbound single lane closure on Eltham Bridge, with work zone barrier. Single lane closure is in place through June 2021. Crews are identifying locations where a future project will repair grout on the bridge.
Westmoreland County
Route 3 Passing Lanes
Construction began Jan. 4 on a project to build eastbound and westbound passing lanes over a 1.5-mile segment of Route 3. When work is complete, Route 3 will become a four-lane undivided road from north of Route 639 (Winter Harbor Road) to east of Route 624 (Longwood Road), with new turn lanes at key intersections. The project will be complete in late Dec. 2021.